Sunny Side Ditch Company Pipeline Project
In 2022, H&T replaced a traditional irrigation ditch with pipeline in order to improve the waterway’s efficiency and sustainability. The Sunnyside Ditch Company requested 3,000 feet of pipe be added to a section of ditch that was restricted by natural barriers and housing developments. The project required excavation work such as clearing and rubbing the area and digging 4-6 feet before installing 48” ADS pipe underground. In addition, two concrete structures were built- an inlet and outlet structure.
In 2023, Darrin and the concrete crew completed a full exterior house foundation with Fox Blocks. This project also included constructing the gables with Fox Blocks. The overall wall height measured in at 30 feet. The exterior foundation was completed in three separate lifts and totaled 250 yards of concrete.